Risk register and risk appetite

In short

A risk register lists each risk a business faces with its score before and after controls, the technique chosen, a named owner and a review date. Risk appetite is the owner's written statement, with numbers, of how much risk the business will accept. Rows outside the appetite become the next set of commitments.

What is a risk register?

A risk register is a living list of the risks that confront a business, internal and external, each with a person responsible for it. IRMI describes it as a catalog of threats that gives a company a shared vocabulary and names who manages each one; RIMS includes it in its enterprise risk management starter kit for the same reason.

For a contractor, a useful register has one row per loss exposure and these columns:

  • The exposure, in plain words ("fall from height, framing crews")
  • Its class: property, liability, personnel or net income
  • An inherent score, before any controls
  • The controls actually in place
  • A residual score, after those controls
  • The technique chosen (see risk control techniques)
  • A risk owner: the named person accountable for the row
  • A last-reviewed date
  • Whether the row is within the owner's risk appetite: yes, no or not decided

How are inherent and residual risk scored?

Inherent risk is the risk before any action is taken to change its likelihood or impact. Residual risk is what remains after the controls in place. A common way to score both is a 5 × 5 grid:

  • Likelihood, 1 to 5: rare, unlikely, possible, likely, almost certain.
  • Impact, 1 to 5: minor, low, moderate, major, severe.
  • Score = likelihood × impact, from 1 to 25.
  • Typical bands: 1 to 5 low, 6 to 12 moderate, 15 to 25 high. No product of two whole numbers from 1 to 5 equals 13 or 14, so the bands leave no gap.

Two rules keep the register honest. Residual can never score higher than inherent on either axis, because a control only makes a loss less likely or less severe. And residual reflects controls in place today; a planned control is a commitment, not a score.

The gap between inherent and residual is what the controls are worth. A row whose residual equals its inherent has no real control on it, whatever the safety manual says.

A worked example (illustrative scores)

Three rows for a hypothetical framing contractor. The scores are judgment calls, which is exactly what a register records.

  1. Fall from height (personnel). Inherent 4 × 5 = 20, high. Controls: weekly inspections and orientation before the first shift. Residual 2 × 5 = 10, moderate. Technique: loss prevention. Likelihood dropped; impact did not, because a fall is still severe when it happens. Owner: safety lead.
  2. Uninsured subcontractor's worker injured on our job (liability). Inherent 3 × 4 = 12, moderate. Controls: subcontractor prequalification and certificate verification before work starts. Residual 1 × 4 = 4, low. Technique: transfer. Owner: office manager.
  3. Tools stolen from an open site (property). Inherent 4 × 2 = 8, moderate. Control: locked storage and lighting. Residual 3 × 2 = 6, moderate. Technique: loss prevention. Owner: superintendent.

Note what the register does not hold: dollars. It tells you where to look and which kind of technique fits. The money lives in the loss history, the cost of risk and the cost-benefit work.

What is risk appetite, and how is it different from risk tolerance?

COSO's enterprise risk management framework defines risk appetite, in substance, as the types and amount of risk an organization is willing to accept, on a broad level, in pursuit of value. Risk tolerance is narrower: the acceptable range of variation around a specific objective. In plain words, the appetite is the sentence and the tolerances are the numbers inside it.

A contractor's appetite might read: "No single retained loss over $100,000; a recordable injury rate under 3.0; no work under a contract we cannot insure." Each clause is testable. "We are conservative" is not, because no row can be checked against it. RIMS and COSO both publish guidance on writing appetite statements that tie to strategy. Whoever drafts the wording, the owner is the one who sets it.

Back to the example. If the contractor's TRIR is an illustrative 4.0 against an appetite of under 3.0, the fall row is marked outside the appetite. That row becomes a commitment for the next quarter, and TRIR becomes a target with a number on it.

What are key risk indicators?

A key risk indicator (KRI) is a metric that gives early warning that an exposure is rising. The closer it sits to the root cause, the more time there is to act. For contractors, good KRIs include:

  • Days from injury to report (a rising number predicts costlier claims)
  • Share of active subcontractors with a valid certificate on file
  • New hires without orientation completed before their first shift
  • Overdue vehicle inspections or driver file reviews

KRIs connect the register to the monthly meeting: each high or out-of-appetite row should have at least one indicator someone watches.

How often should a risk register be reviewed?

At least once a year, and whenever the business changes: a new trade, a new state, a large new customer or a new contract form. A row that has not been reviewed in more than a year should be flagged as overdue. A register written once and filed is step 1 of the process done once and forgotten; the one-page risk plan guide shows how to keep the short version in front of the owner.

Quick answers

What should be included in a risk register?

At minimum: the risk, its category, a score before and after controls, the controls in place, the treatment chosen, a named owner and a review date. Many registers also record whether each risk sits within the stated risk appetite.

What is the difference between inherent and residual risk?

Inherent risk is the risk before any action to reduce it. Residual risk is what remains after the controls actually in place. The gap between them shows what those controls are worth.

What is an example of a risk appetite statement for a contractor?

"No single retained loss over $100,000 and a recordable injury rate under 3.0" is a usable example because each clause can be measured. Statements without numbers, such as "moderate risk," cannot be tested against anything.

Terms in this entry
Residual risk
The risk that remains after the controls actually in place. It is compared with inherent risk, the level before any controls, to show what the controls are worth.
Risk appetite
The types and amount of risk a business is willing to accept in pursuit of its goals, best written with numbers so each risk can be tested against it.
Sources and standards
  1. Risk register (definition) · IRMI
  2. ERM Starter Kit: Risk Register · RIMS
  3. Steps to Successful Risk Taking: Developing Effective Risk Appetite and Tolerance Statements · RIMS
  4. Glossary: risk appetite (COSO ERM definition) · NIST Computer Security Resource Center
  5. Risk Appetite: Critical to Success · COSO

Worked examples use illustrative numbers unless a source is named. This entry explains general concepts; it isn't legal, tax or coverage advice for a specific policy or contract.

Brandon Junkin
Brandon Junkin, Founder of Frost

I built Frost, the risk management platform approved insurance agents use to run contractor risk programs. Seven years in IT taught me to fix the cause, not the symptom. More about Frost

Related in the Library
The risk management processLoss exposures: the four classesA loss exposure is any condition that presents the possibility of a loss, whether or not a loss ever happens.The risk management processRisk control techniques and risk financingRisk control techniques change the loss itself: avoidance, loss prevention, loss reduction, separation, duplication and diversification.Safety and operationsTRIR and DART rates explainedTRIR (total recordable incident rate) is recordable cases times 200,000, divided by total hours worked.Cost of riskTotal cost of risk (TCOR) for contractorsTotal cost of risk (TCOR) is everything a business pays or loses in a year because risk exists: premiums, taxes and fees, retained and uninsured losses, the indirect cost of injuries, and what it spends to manage risk.The risk management processThe risk management process, step by stepThe risk management process is a six-step loop for deciding what a business will do about the losses it could suffer: identify loss exposures, analyze them, examine which techniques could treat them, select the best ones, implement them, and monitor results.Resources · 5 min guideHow to write a contractor risk plan on one pageMost risk plans die by March. Here's a simple one-page template with a name and a date on every line, so yours doesn't.Resources · 5 min guideSubcontractor certificates of insurance and what they don't proveA certificate looks like proof, but it's only a snapshot. Here's what it shows, what it doesn't and a simple system so lapsed sub coverage never lands on your audit.

Want this run for your company?

Approved Frost agents deliver full-service fractional risk management on Frost: your total cost of risk, a plan with owners and documented savings, at a fraction of the cost of a risk department.

Find an approved agent